Taifeng cleaning contributes to the new record of start-up of China's large ethylene cracking u
At 1:16 p.m. on August 17, the cracking furnace of ethylene plant of
Gulei refining and chemical integration project in Zhangzhou, Fujian,
the largest petrochemical project jointly invested by both sides of the
Taiwan Strait, was fed, and it took 31 hours to produce qualified
ethylene. It took less than three months from the project delivery to
the successful start-up, setting a new record for Sinopec's large
ethylene start-up in recent years.
Shandong Taifeng Cleaning Technology Co., Ltd. overcame the impact of the epidemic situation, successfully completed the pre commissioning cleaning of Gulei petrochemical ethylene cracking unit, and made an important contribution to the new record of start-up for large ethylene in China.